Welcome to the communications link for the "Creekside" project at Ingleside at Rock Creek. We have been working with ANC 3/4G, the Ingleside Expansion Task Force (as established by the ANC 3/4G), our neighbors, Temple Sinai, the Carnegie Institution of Washington, Northwest Neighbors Village and of course, our Ingleside residents to plan for the future of our campus. The need for additional apartments for Independent Living has grown past our capacity. Our Assisted Living building is over fifty years old and no longer meets the needs of our residents. Our nursing home is over thirty years old and is institutional in nature rather than home like.

This is not a marketing site for selling new buildings. This is strictly an informational site to keep all interested parties up to date with our real estate development and construction process.

 

What's Happening  

Entering & Visiting the IRC Property

Starting November 4, 2019, the entrance from Military Road will be the only means of entering and exiting the property. We expect this arrangement to e in effect until Spring 2020 when the new bio-retention structures are built.

Broad Branch Road – NOTICE OF FUTURE TEMPORARY CLOSURE

  • The general contractor anticipates one more closure / detour to be in effect to place a permanent DDOT-approved roadway patch over the newly-installed underground utility crossings. Detour signs will be covered up until this time.
  • Target start date has been postponed due to weather delays; rescheduled date(s) to be confirmed.
  • The future closure will occur Mon-Friday, 9:30 a.m. through 3:30 p.m. No closures will occur on weekends.

Delivery Milestones

  • Health Services (Building 1) – Completed June 2019; Operating July 2019.
  • Center For Healthy Living (Lower floor of Buildings 8 & 9) – Completed November 2019; Operating December 2019.
  • Independent Living Residences (Upper floors of Buildings 8 &9) – Target Completion December 2019; Move-Ins begin January 2020.
  • Cross-Campus Connector Tunnel (Building 3) and Elliptical Courtyard – Target Completion August, 2020.
  • Grand Opening – Anticipated for Autumn 2020!

 

Construction Progress     progresswebcam

 

Please see our most recent IRC monthly WING Flyer

 

If you have questions about real estate development, construction issues or information posted on this website, please CONTACT US



Ingleside at Rock Creek
3050 Military Road, NW
Washington, DC 20015



ircdc.org

 

WING





Washington, D.C.'s faith based, not-for-profit continuing care retirement community.

3050 Military Road, NW Washington, DC 20015 Main Number: (202) 363-8310